Based on rule of thumb any excavation depth of more than 1.5m requires temporary shoring and sheet pile is the commonest and safest option.
Also depth of sheet pile is 2/3 into ground with 1/3 as excavation depth.
Actual design depends on soil condition and adjacent structures.